Parkstone Grammar School – Poole
| Cost | £1.25m inc Fees (excluding VAT) |
| Opened | Autumn 2009 |
| Location | Parkstone Grammar School for Girls, Poole, Dorset |
| Project | Four badminton court sports hall with equipment storage, adjoining the existing gymnasium and amenities. Two additional changing rooms, accessible changing toilets and amenities. Classroom / Meeting Room Link corridor to existing building. |
| Client | Parkstone Grammar School |
| Project Manager | Ball Hall Ltd |
| Employer’s Agent | Daniel Connal Partnership LLP, Colchester |
| Architect | Clague Architects, Canterbury |
| Main Contractor | Acheson Construction Ltd, Dorchester |
| Operator | Daniel Connal Partnership PPL, Colchester |
| Sports Floor | Dynamik Sports Floors |
| Grant Aid | None |